Computer aided construction system for submarine excavation of 4A anchorage for Kurushima Bridge

Masahiro Harada, Manabu Komura, Yoshimi Hasegawa, Katsuhiko Nishida, Motoh Tsunoda, Masaki Hirano

Research output: Contribution to journalArticle

Abstract

For the submarine excavation of the anchorage foundation for the Kurushima Bridge connecting Honshu and Sikoku, a computer aided construction system was set up and used to strictly control all the construction processes, including the submarine topography survey prior to excavation, routine excavation, finish and confirmation of the excavated sea bed. The result was savings in time and manpower, and improvement in quality. High quality control of construction was achieved. In this paper we will introduce the computer aided construction system that was developed for the above project. At the same time, we will report on research into computer aided construction, which has shown great promise as a new construction method for marine projects.

Original languageEnglish
Pages (from-to)13-22
Number of pages10
JournalDoboku Gakkai Rombun-Hokokushu/Proceedings of the Japan Society of Civil Engineers
Issue number504 pt 6-25
Publication statusPublished - 1994 Dec 1
Externally publishedYes

Fingerprint

Anchorages (foundations)
Excavation
Topography
Quality control

ASJC Scopus subject areas

  • Engineering(all)

Cite this

Computer aided construction system for submarine excavation of 4A anchorage for Kurushima Bridge. / Harada, Masahiro; Komura, Manabu; Hasegawa, Yoshimi; Nishida, Katsuhiko; Tsunoda, Motoh; Hirano, Masaki.

In: Doboku Gakkai Rombun-Hokokushu/Proceedings of the Japan Society of Civil Engineers, No. 504 pt 6-25, 01.12.1994, p. 13-22.

Research output: Contribution to journalArticle

Harada, Masahiro ; Komura, Manabu ; Hasegawa, Yoshimi ; Nishida, Katsuhiko ; Tsunoda, Motoh ; Hirano, Masaki. / Computer aided construction system for submarine excavation of 4A anchorage for Kurushima Bridge. In: Doboku Gakkai Rombun-Hokokushu/Proceedings of the Japan Society of Civil Engineers. 1994 ; No. 504 pt 6-25. pp. 13-22.
@article{162409963f6241dbb2e05205c6258828,
title = "Computer aided construction system for submarine excavation of 4A anchorage for Kurushima Bridge",
abstract = "For the submarine excavation of the anchorage foundation for the Kurushima Bridge connecting Honshu and Sikoku, a computer aided construction system was set up and used to strictly control all the construction processes, including the submarine topography survey prior to excavation, routine excavation, finish and confirmation of the excavated sea bed. The result was savings in time and manpower, and improvement in quality. High quality control of construction was achieved. In this paper we will introduce the computer aided construction system that was developed for the above project. At the same time, we will report on research into computer aided construction, which has shown great promise as a new construction method for marine projects.",
author = "Masahiro Harada and Manabu Komura and Yoshimi Hasegawa and Katsuhiko Nishida and Motoh Tsunoda and Masaki Hirano",
year = "1994",
month = "12",
day = "1",
language = "English",
pages = "13--22",
journal = "Doboku Gakkai Rombun-Hokokushu/Proceedings of the Japan Society of Civil Engineers",
issn = "0289-7806",
number = "504 pt 6-25",

}

TY - JOUR

T1 - Computer aided construction system for submarine excavation of 4A anchorage for Kurushima Bridge

AU - Harada, Masahiro

AU - Komura, Manabu

AU - Hasegawa, Yoshimi

AU - Nishida, Katsuhiko

AU - Tsunoda, Motoh

AU - Hirano, Masaki

PY - 1994/12/1

Y1 - 1994/12/1

N2 - For the submarine excavation of the anchorage foundation for the Kurushima Bridge connecting Honshu and Sikoku, a computer aided construction system was set up and used to strictly control all the construction processes, including the submarine topography survey prior to excavation, routine excavation, finish and confirmation of the excavated sea bed. The result was savings in time and manpower, and improvement in quality. High quality control of construction was achieved. In this paper we will introduce the computer aided construction system that was developed for the above project. At the same time, we will report on research into computer aided construction, which has shown great promise as a new construction method for marine projects.

AB - For the submarine excavation of the anchorage foundation for the Kurushima Bridge connecting Honshu and Sikoku, a computer aided construction system was set up and used to strictly control all the construction processes, including the submarine topography survey prior to excavation, routine excavation, finish and confirmation of the excavated sea bed. The result was savings in time and manpower, and improvement in quality. High quality control of construction was achieved. In this paper we will introduce the computer aided construction system that was developed for the above project. At the same time, we will report on research into computer aided construction, which has shown great promise as a new construction method for marine projects.

UR - http://www.scopus.com/inward/record.url?scp=0028734208&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=0028734208&partnerID=8YFLogxK

M3 - Article

AN - SCOPUS:0028734208

SP - 13

EP - 22

JO - Doboku Gakkai Rombun-Hokokushu/Proceedings of the Japan Society of Civil Engineers

JF - Doboku Gakkai Rombun-Hokokushu/Proceedings of the Japan Society of Civil Engineers

SN - 0289-7806

IS - 504 pt 6-25

ER -