Steel pipe sheet pile cutoff walls built up by installing steel pipe sheet piles (SPSPs) in coastal waste landfill sites are important elements for preventing leakage of leaching from the reclaimed waste to the open sea. Adhesion with the peripheral ground has to be maintained in the installation of SPSPs for manifestation of the cutoff function of the SPSPs with joint sections. In this study, attention is paid to the disturbed area generated in the peripheral ground around the steel pipe sheet pile cutoff walls. Moreover, by using seepage and advection/dispersion analysis, we evaluated the impact of the disturbed area on the environmental preservation function of coastal waste landfill sites as a whole, the effect of the installation method which suppresses the formation of the disturbed area and the influence of soil improvement by the sand compaction pile method. One of the results of this study has shown that the disturbed area generated in the lower deposition clay layer greatly influences the quantity of leakage of toxic substances in a specific route. On the other hand, the installation of SPSPs by using soil cement, in which the soil improvement of the periphery ground is undertaken, is effective in suppressing the leakage of toxic substances.

Original languageEnglish
Pages (from-to)217-224
Number of pages8
JournalGeotechnical Engineering
Volume40
Issue number4
Publication statusPublished - 2009 Dec
Externally publishedYes

Fingerprint

cutoff wall
Land fill
Steel pipe
Piles
Environmental impact
landfill
pile
environmental impact
pipe
steel
leakage
soil improvement
toxic substance
Soil cement
Soils
Advection
Seepage
evaluation
adhesion
Leaching

Keywords

  • Containment
  • Environmental impact
  • Steel pipe sheet pile
  • Vertical cutoff wall
  • Waste landfill site

ASJC Scopus subject areas

  • Geotechnical Engineering and Engineering Geology
  • Civil and Structural Engineering

Cite this

Environmental impact evaluation on construction of vertical cutoff walls in landfill sites. / Inazumi, Shinya; Kimura, M.

In: Geotechnical Engineering, Vol. 40, No. 4, 12.2009, p. 217-224.

Research output: Contribution to journalArticle

@article{34b54be23cf248b0a1a4b55660813772,
title = "Environmental impact evaluation on construction of vertical cutoff walls in landfill sites",
abstract = "Steel pipe sheet pile cutoff walls built up by installing steel pipe sheet piles (SPSPs) in coastal waste landfill sites are important elements for preventing leakage of leaching from the reclaimed waste to the open sea. Adhesion with the peripheral ground has to be maintained in the installation of SPSPs for manifestation of the cutoff function of the SPSPs with joint sections. In this study, attention is paid to the disturbed area generated in the peripheral ground around the steel pipe sheet pile cutoff walls. Moreover, by using seepage and advection/dispersion analysis, we evaluated the impact of the disturbed area on the environmental preservation function of coastal waste landfill sites as a whole, the effect of the installation method which suppresses the formation of the disturbed area and the influence of soil improvement by the sand compaction pile method. One of the results of this study has shown that the disturbed area generated in the lower deposition clay layer greatly influences the quantity of leakage of toxic substances in a specific route. On the other hand, the installation of SPSPs by using soil cement, in which the soil improvement of the periphery ground is undertaken, is effective in suppressing the leakage of toxic substances.",
keywords = "Containment, Environmental impact, Steel pipe sheet pile, Vertical cutoff wall, Waste landfill site",
author = "Shinya Inazumi and M. Kimura",
year = "2009",
month = "12",
language = "English",
volume = "40",
pages = "217--224",
journal = "Geotechnical Engineering",
issn = "0046-5828",
publisher = "Southeast Asian Geotechnical Society",
number = "4",

}

TY - JOUR

T1 - Environmental impact evaluation on construction of vertical cutoff walls in landfill sites

AU - Inazumi, Shinya

AU - Kimura, M.

PY - 2009/12

Y1 - 2009/12

N2 - Steel pipe sheet pile cutoff walls built up by installing steel pipe sheet piles (SPSPs) in coastal waste landfill sites are important elements for preventing leakage of leaching from the reclaimed waste to the open sea. Adhesion with the peripheral ground has to be maintained in the installation of SPSPs for manifestation of the cutoff function of the SPSPs with joint sections. In this study, attention is paid to the disturbed area generated in the peripheral ground around the steel pipe sheet pile cutoff walls. Moreover, by using seepage and advection/dispersion analysis, we evaluated the impact of the disturbed area on the environmental preservation function of coastal waste landfill sites as a whole, the effect of the installation method which suppresses the formation of the disturbed area and the influence of soil improvement by the sand compaction pile method. One of the results of this study has shown that the disturbed area generated in the lower deposition clay layer greatly influences the quantity of leakage of toxic substances in a specific route. On the other hand, the installation of SPSPs by using soil cement, in which the soil improvement of the periphery ground is undertaken, is effective in suppressing the leakage of toxic substances.

AB - Steel pipe sheet pile cutoff walls built up by installing steel pipe sheet piles (SPSPs) in coastal waste landfill sites are important elements for preventing leakage of leaching from the reclaimed waste to the open sea. Adhesion with the peripheral ground has to be maintained in the installation of SPSPs for manifestation of the cutoff function of the SPSPs with joint sections. In this study, attention is paid to the disturbed area generated in the peripheral ground around the steel pipe sheet pile cutoff walls. Moreover, by using seepage and advection/dispersion analysis, we evaluated the impact of the disturbed area on the environmental preservation function of coastal waste landfill sites as a whole, the effect of the installation method which suppresses the formation of the disturbed area and the influence of soil improvement by the sand compaction pile method. One of the results of this study has shown that the disturbed area generated in the lower deposition clay layer greatly influences the quantity of leakage of toxic substances in a specific route. On the other hand, the installation of SPSPs by using soil cement, in which the soil improvement of the periphery ground is undertaken, is effective in suppressing the leakage of toxic substances.

KW - Containment

KW - Environmental impact

KW - Steel pipe sheet pile

KW - Vertical cutoff wall

KW - Waste landfill site

UR - http://www.scopus.com/inward/record.url?scp=84857335638&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84857335638&partnerID=8YFLogxK

M3 - Article

AN - SCOPUS:84857335638

VL - 40

SP - 217

EP - 224

JO - Geotechnical Engineering

JF - Geotechnical Engineering

SN - 0046-5828

IS - 4

ER -